Milestones

2011
  • Aug. Production capacity is estimated to reach to 410 MW
2010
  • Jul. Production capacity reached to 200 MW
  • Aug. Capital Increased to USD 59 millions
2009
  • Feb. Capital Increased to USD 40 million
  • May. Eversol Shares Traded at TEM (Taiwan Emerging Market)
2008
 
  • Feb. Miaoli Plant construction started
  • May. First DSS450 furnace delivered and installation commenced
  • Jun. First polysilicon ingot produced
  • Jul. First PV wafer produced from Miaoli plant
  • Aug. Plant construction completed
  • Dec. Production capacity reached to 150 MW
2007
  • Sep. Company established
  • Dec. Capital Increased to USD 28 millions